Nine Mile Falls Elementary
Nine Mile Falls, WA

Built on the same contract as Lake Spokane Elementary, This project is yet another example of effectiveness in managing complexities of phased construction within owner-occupied buildings. The project required three major phases of work with planned owner move-ins over school breaks. Phasing was further impacted by the necessity to relocate an existing septic drain field to make way for construction of the south addition. Not only were we successful in managing an effective phasing strategy, we were able to leverage the completion schedule to shorten by two months, allowing the owner to fully occupy both schools for the start of the 2009-2010 school year. Work was performed as part of a GC/CM Joint Venture. 

Client:
Nine Mile Falls School District
Architect:
Architects West